We're a demolition contractor, not an asbestos company, so we don't set abatement prices. On our jobs the survey and any removal are done by licensed asbestos firms and listed as their own line items, which is why owners ask us what those numbers should look like. The cost figures below are published national estimates, each with its source. South Florida prices can land higher or lower, so use them to judge whether a quote is in the normal range, not as a price list.
Asbestos comes up most on commercial demolition, where a survey is required for every building, but older houses can have it too.
At a glance
Asbestos testing and removal costs at a glance
These are national figures from two cost guides. They give you a range to check a quote against, not a South Florida price list.
| Item | Typical cost | Source |
|---|---|---|
| Asbestos test | Typical cost: $231 to $777, average about $484 | Source: Angi |
| Inspection and testing | Typical cost: $250 to $800 | Source: This Old House |
| Air testing | Typical cost: $200 to $800, usually around $500 | Source: Angi |
| Removal, typical job | Typical cost: $1,215 to $3,285, average about $2,250 | Source: Angi, 2026 |
| Interior removal | Typical cost: $5 to $20 per square foot | Source: Angi; This Old House |
| Exterior removal (roofs, siding) | Typical cost: $50 to $150 per square foot | Source: Angi; This Old House |
| Encapsulation instead of removal | Typical cost: $2 to $6 per square foot | Source: Angi; This Old House |
| Disposal | Typical cost: $10 to $50 per cubic yard | Source: Angi; This Old House |
Angi's removal figures are based on 3,805 projects reported by its pros. This Old House says its figures come from Angi and HomeAdvisor estimates (updated April 1, 2026). Neither is specific to Florida.
By material
What removal costs by material
The material matters more than anything else, because it decides how the work is set up and how much containment it needs.
| Material | Typical removal cost |
|---|---|
| Floor tile (like 9 x 9 VCT) | Typical removal cost: $5 to $15 per square foot |
| Popcorn ceiling | Typical removal cost: $9 to $20 per square foot |
| Walls and drywall | Typical removal cost: $8 to $13.50 per square foot |
| Pipe insulation | Typical removal cost: $5 to $15 per square foot, or $2 to $5 per linear foot for pipe wrap |
| HVAC ducts | Typical removal cost: $35 to $55 per square foot |
| Attic insulation | Typical removal cost: $11 to $25 per square foot |
| Siding | Typical removal cost: $3 to $15 per square foot |
| Roof and shingles | Typical removal cost: $50 to $120 per square foot |
Source: Angi, 2026. Removal only. Putting in new flooring, drywall, ducts or roofing afterward is a separate cost.
By size
What removal costs by area
Small jobs cost more per square foot, because the setup, containment, air testing and disposal trip are much the same whether the area is 100 square feet or 300.
| Area of material | Typical interior removal cost |
|---|---|
| 100 to 200 square feet | Typical interior removal cost: $1,250 to $2,500 |
| 200 to 400 square feet | Typical interior removal cost: $2,500 to $5,000 |
| 400 to 600 square feet | Typical interior removal cost: $5,000 to $7,500 |
| 600 to 1,000 square feet | Typical interior removal cost: $7,500 to $12,500 |
Source: Angi, 2026.
Price drivers
What makes an asbestos job cost more or less
Two jobs with the same square footage can come in far apart. These are the reasons.
The material and its condition
Material that crumbles easily, like old pipe insulation or a sprayed ceiling, needs tighter containment than intact floor tile. Damaged material costs more to handle than material in good shape.
How much there is
More material means more labor and more disposal, but the price per square foot usually drops as the job gets bigger.
How hard it is to reach
Material behind walls, above ceilings, in an attic or on a roof takes more work to get to and to contain.
Containment and air testing
Interior jobs are usually sealed off, and many end with air testing before the area is cleared. Air testing alone typically runs $200 to $800.
Disposal
Asbestos waste goes to a landfill that accepts it, packaged and documented. Disposal typically runs $10 to $50 per cubic yard.
Leaving it in place
Sealing material in place, called encapsulation, usually costs 15% to 25% less than removal. It only works when the material stays and isn't disturbed, so it's not an option for anything being demolished.
South Florida rules
When a survey and notice are required in South Florida
Whether you need a survey depends on the type of building and whether it's a demolition or a renovation, and each county runs its own program.
| Situation | What's required |
|---|---|
| Demolishing a commercial building or a residential building with 5 or more units | What's required: An asbestos survey, and a written notice filed at least 10 working days before work starts, even if no asbestos is found. |
| Renovating one of those buildings | What's required: A notice when the regulated asbestos to be disturbed reaches about 160 square feet, 260 linear feet or 35 cubic feet. |
| Demolishing a single-family home | What's required: Generally exempt from the federal notice, but some cities ask for an asbestos statement or the county certificate with the permit, so check before you assume. |
| Miami-Dade County | What's required: DERM handles asbestos notices and charges on its own fee schedule. |
| Broward County | What's required: The SRRA is filed online at least 10 working days ahead. The county lists a $100 review fee, with owner-occupied homes of four or fewer units exempt. |
| Palm Beach County | What's required: The Department of Health wants the notice, the survey and the fee before it gives written approval to start. |
Where the state DEP handles the notice, its fee is $200, or $100 filed and paid online.
Florida licensing
Who can test and remove asbestos in Florida
Florida licenses asbestos work under Chapter 469 of the Florida Statutes, and it separates the people who survey from the people who remove.
The survey: a licensed asbestos consultant
Florida law says no one may conduct an asbestos survey unless trained and licensed as an asbestos consultant. A general home inspection is not an asbestos survey.
The removal: a licensed asbestos contractor
Asbestos abatement work has to be done by a contractor licensed by the state for it. A general contractor's license, ours included, doesn't cover abatement.
The homeowner exemption
An owner can remove asbestos from a home they live in, as long as the home isn't for sale or lease and the owner personally signs the building permit application. A house being torn down to sell the lot, or a rental, doesn't qualify.
Check the license
Both licenses can be looked up on the Florida DBPR website. Ask for the license number on the survey report and on the abatement contract.
With a demolition
How the asbestos work fits into a demolition
Asbestos always comes first, and the order below is what keeps a demolition permit from stalling.
Order the survey early
Get the survey before you collect demolition bids, so every contractor prices the same scope and nobody guesses.
Read the results
If nothing regulated is found, the asbestos part may stop at the survey and any required notice. If something is found, the report says what and where.
File the notice
For regulated buildings, the notice goes to the county program at least 10 working days before work starts.
Remove the material
The licensed abatement contractor removes what has to come out before demolition, packages it and sends it to an approved landfill.
Clear the area and demolish
Once the abatement is done and documented, the demolition goes ahead under the permit.
Before you sign
How to read an asbestos quote
A good quote tells you exactly what's being removed and what's included.
It names the material and the amount
The quote should match the survey: which materials, how many square or linear feet, and where they are.
It says what's included
Look for containment, air testing, disposal and the notice. If one is missing, ask whether it's extra.
It shows both licenses
The survey firm and the abatement contractor should each have a Florida license number on their paperwork.
It leaves out what comes after
New flooring, drywall or a new roof are separate. Don't compare an abatement price against a quote that includes replacement.
Related
Keep reading
Asbestos and demolition in Florida
The rules, the notice and who handles it in each county.
Popcorn ceilings and asbestos
Testing, your options and who can do the work.
VCT floor tile removal
How old floor tile comes out, and when it's an abatement job.
Commercial demolition cost
What drives the price of a commercial teardown.
Common questions
Frequently asked questions
How much does asbestos testing cost in Florida?
Published national estimates put asbestos testing at about $231 to $777, with an average around $484 (Angi), and inspection and testing at $250 to $800 (This Old House). The size of the building and the number of samples drive the price. In Florida, an asbestos survey has to be done by a licensed asbestos consultant.
How much does asbestos removal cost per square foot?
Interior removal typically runs $5 to $20 per square foot and exterior work like roofs and siding $50 to $150, according to Angi and This Old House. Floor tile is usually $5 to $15 and popcorn ceilings $9 to $20 per square foot.
What would it cost to remove 134 square feet of asbestos floor tile?
At Angi's floor tile range of $5 to $15 per square foot, the removal itself works out to about $670 to $2,010. Small jobs often land higher per square foot because setup, containment, air testing and disposal cost about the same either way, and Angi puts 100 to 200 square feet of interior removal at $1,250 to $2,500. In a commercial building, check whether a notice is needed: 134 square feet is under the 160 square foot renovation threshold, but a full demolition needs a notice regardless.
Do I need an asbestos survey to demolish a house in South Florida?
Single-family homes are generally exempt from the federal notice, but some cities ask for an asbestos statement or the county certificate with the demolition permit. Commercial buildings and residential buildings with five or more units always need a survey and a notice at least 10 working days before demolition.
Can I remove asbestos myself in Florida?
Only in a home you own and live in, that isn't for sale or lease, and you have to personally sign the building permit application. Otherwise abatement has to be done by a state-licensed asbestos contractor.
Does homeowners insurance pay for asbestos removal?
Don't count on it. Coverage depends on the policy and on why the asbestos is being removed, so read your policy and ask your agent before you plan around it.
Is asbestos removal included in a demolition quote?
Ask. On our jobs the survey and any abatement are done by licensed asbestos firms and listed as separate line items, so you can see exactly what they cost. A quote that doesn't mention asbestos at all on an older building is a quote that may change later.
Cost figures are national estimates published by Angi (2026) and This Old House (updated April 1, 2026), not quotes, and South Florida prices vary. Regulatory information is based on Chapter 469 of the Florida Statutes and county asbestos programs as of November 2026. Rules and fees change, so confirm with your county program and a licensed asbestos consultant before you start.