The new exemption is real, and for small cosmetic work it saves owners a trip through the permit system. But it was written for things like flooring and cabinets, not for taking buildings down. The exclusions are broad, the flood zone rule knocks out a lot of South Florida, and the city has to approve each request in writing before anyone starts. Below is how each kind of demolition job lines up against the actual wording of the statute.
When a job does need a permit, we pull it as part of our residential demolition service across Miami-Dade, Broward and Palm Beach.
The law
What does Florida's $7,500 permit exemption say?
HB 803 became Chapter 2026-63, Laws of Florida, signed May 6, 2026, and took effect July 1, 2026. The exemption is in section 553.79(1)(g) of the Florida Statutes.
What it exempts
Local governments must exempt the owner of a single-family dwelling, or the owner's contractor, from getting a building permit for "any work valued at less than $7,500" on the owner's property. Less than $7,500, not $7,500 or less.
What it never covers
Any electrical, plumbing, structural, mechanical or gas work, no matter the value. And any property that is partially or entirely in a flood hazard area as the Florida Building Code defines it.
No splitting
A project may not be divided into smaller projects to get under the limit. A $20,000 kitchen remodel can't be filed as a $6,000 tear-out plus everything else.
It isn't automatic
The owner or contractor has to submit a written request with the contract or other documents showing what the work is and what it costs. The city decides.
The city owes you nothing for it
The statute says the local government "has no legal duty" to the owner or contractor for exempted work. No permit also means no inspector checking the work for you.
Job by job
Which demolition jobs can qualify for the $7,500 exemption?
Full teardowns, pools and interior guts don't qualify. Cosmetic tear-outs and some flatwork removal can, if the property is outside a flood hazard area and the city approves it first.
| Job | Can it qualify? | Why |
|---|---|---|
| Full house demolition | Can it qualify?: No | Why: Demolition is still listed in 553.79(1)(a) as work that needs a permit. Taking down a house means removing structure and disconnecting electric, water and sewer, which are all excluded trades. The cost is also far above $7,500. |
| Interior gut (walls, ceilings, kitchens, baths) | Can it qualify?: Almost never | Why: Interior walls carry wiring and plumbing, and some carry load. Once you cut a circuit, cap a pipe or touch framing, the work is excluded. |
| Flooring, cabinets, countertops or drywall tear-out | Can it qualify?: Possibly | Why: This is the cosmetic work the exemption was written for. Watch the details: pulling a sink, dishwasher or disposal means a plumbing disconnect, and old tile, mastic and drywall compound can contain asbestos. |
| Shed or detached garage | Can it qualify?: Unlikely | Why: Cities treat sheds as structural. Pinecrest, for example, lists sheds under structural work. A shed or garage with power means electrical work too. |
| Pool removal or fill-in | Can it qualify?: No | Why: The shell is structural, the lines get cut and capped, the pump and lights are electrical, and pool barrier rules under Chapter 515 still apply. |
| Patio, walkway or slab removal | Can it qualify?: Possibly | Why: Breaking out flatwork isn't one of the excluded trades, so a small patio outside a flood zone can qualify. A driveway apron in the right of way still needs public works approval. |
| Deck or screen enclosure removal | Can it qualify?: Usually no | Why: Decks and aluminum screen enclosures are built to structural and wind load rules, and building departments treat them as structural work. |
| Fence removal | Can it qualify?: Ask the city | Why: Taking an old fence down is rarely the issue. Putting up the new one needs a zoning permit even when the building permit is waived. |
| Duplex, condo, apartment or commercial interior | Can it qualify?: No | Why: The exemption only covers single-family dwellings. Fort Lauderdale lists condos, multifamily and commercial properties as excluded. |
Each building official makes the final call. This table reflects the statute and the published guidance of Fort Lauderdale, Miami, Pompano Beach and Pinecrest as of November 2026.
The flood zone catch
Is your property in a flood hazard area?
If any part of the lot is in a flood hazard area, the exemption is off the table, whatever the work costs. Along the coast and in low-lying parts of South Florida, that rules out a lot of homes.
Partly counts
The statute says "partially or entirely." A lot that a flood zone line only clips still loses the exemption.
Which zones
The City of Miami and Pompano Beach both list zones A, AE, AH, AO, AR, A99, V and VE as excluded. Miami lists zones X and D as outside the special flood hazard area.
How to check
Look up the address on FEMA's Flood Map Service Center or your city's GIS map, or check the flood zone on your survey or elevation certificate. If it's close, ask the building department before you file.
Why it matters for teardowns
Flood zones also drive what you can build back. If a house in a flood zone is coming down, read up on elevation and substantial improvement first.
The process
How do you request the $7,500 permit exemption?
Get a written estimate, confirm the flood zone, file the city's exemption form, and don't start until you have the approval in writing.
Write down the whole scope
List everything the project includes, not just the tear-out. If the full project is $7,500 or more, or includes any excluded trade, the exemption doesn't fit.
Get a written estimate or contract
The statute requires a contract or other documents showing the nature and value of the work. Fort Lauderdale asks for a cost estimate, and Pompano Beach asks for an itemized estimate or signed contractor agreement.
Confirm the flood zone
Check the property against the flood map before you file. Partial counts.
File the city's exemption request
Each city has its own form and portal. Fort Lauderdale takes it through LauderBuild, Miami through an online request form, and Pompano Beach through its ePlan portal.
Wait for written approval
Nothing starts before the city says yes in writing. Miami requires the approval letter to be posted on site before work begins.
Keep the letter and finish on time
Keep the approval with your property records. Pompano Beach gives you 180 days from its acknowledgment letter to finish the work.
City by city
How do South Florida cities handle the exemption?
The statute is the same everywhere, but each city sets its own request process.
| City | How to apply | What stands out |
|---|---|---|
| Fort Lauderdale | How to apply: Residential Permit Exemption Request form plus a job cost estimate, submitted through LauderBuild | What stands out: Excludes condos, multifamily and commercial. Window replacements and AC units are not exempt. Applications filed before July 1, 2026 don't qualify. |
| City of Miami | How to apply: Online Building Permit Exemption Request (HB 803) form | What stands out: The approval must be posted on site before work starts. It doesn't authorize tree removal, trimming or work that harms protected trees. |
| Pompano Beach | How to apply: Exemption request through the ePlan portal with a signed affidavit and itemized estimate | What stands out: No fee for the request. Review within 3 business days of a complete submission, 180 days to finish, 15 days to appeal a denial. Sub-permits for trades are filed at the same time. |
From each city's published HB 803 guidance, November 2026. Other cities set up their own forms, so check yours.
Still on you
What doesn't the $7,500 exemption waive?
The exemption only removes the building permit. Asbestos rules, tree rules, zoning, HOA approval, pool barrier law and the building code itself still apply.
Asbestos
Old floor tile, mastic, popcorn ceilings and drywall compound can contain asbestos. Skipping the permit doesn't change what's in the material. Test before you tear it out.
Trees
Tree removal and work near protected trees still need their own approvals. Miami says so directly on its exemption page.
Zoning, HOA and the right of way
Setbacks, zoning permits, HOA rules and public works approvals for the right of way all still apply. Miami notes that other departments may still require their own approvals.
Pool barriers
Pompano Beach points out that a pool barrier must stay in continuous compliance with Chapter 515 during any exempt work.
The code
Exempt work still has to meet the Florida Building Code. There's just no inspector checking it.
Licensing
Paid work still has to be done by properly licensed contractors. Pompano Beach repeats this in its guidance.
From the field
When does the exemption help, and when does it backfire?
It helps on a small cosmetic tear-out with nothing else attached. It backfires when the tear-out is really the first phase of a bigger job.
It helps
Pulling up old carpet or laminate, removing a run of cabinets with no plumbing behind them, taking out a small patio on a lot outside the flood zone. A short form instead of a permit can save a couple of weeks.
It backfires
When the tear-out is the start of a remodel. The remodel needs a permit for the plumbing and electrical anyway, and the no-splitting rule means the demolition belongs in that permit, not in a separate exemption.
Selling or rebuilding later
Work that should have been permitted can come up at inspection when you sell, refinance or apply to build. An exemption approval in your records shows it was done properly. Work done without one doesn't.
When in doubt, permit it
A demolition permit protects you with an inspection and a closed record. On anything structural, anything with utilities or anything in a flood zone, that's the path the law requires anyway.
Related
Keep reading
My house flooded: what to tear out first
Document, flood cut, permits and mold.
Do you need a permit to demolish?
What every demolition permit asks for.
Kitchen and bathroom demolition
Tear-outs before a remodel.
Shed, garage and carport demolition
Small structures, slabs and setbacks.
Driveway and patio removal
Breaking out concrete and pavers.
Pool removal vs. fill-in
The two ways to get rid of a pool.
Popcorn ceilings and asbestos
What to test before you scrape.
Common questions
Frequently asked questions
Do I need a permit to demolish a house in Florida after HB 803?
Yes. The $7,500 exemption doesn't apply to structural, electrical or plumbing work, and a house demolition always involves all three. Florida Statute 553.79(1)(a) still requires a permit for demolition.
Can I tear out my kitchen without a permit under the $7,500 rule?
Only if the work stays cosmetic, costs less than $7,500, the property is outside a flood hazard area and the city approves your written request first. Disconnecting the sink, dishwasher or any wiring is plumbing or electrical work, which is excluded.
Do I need a permit to remove a shed in Florida now?
Usually yes. Building departments treat sheds as structural work, and a shed with power adds electrical work. Some cities never required a permit for a very small prefab shed. Ask your building department.
Does the $7,500 exemption apply in a flood zone?
No. The exemption doesn't apply to any property that is partially or entirely in a flood hazard area as defined by the Florida Building Code, including zones A, AE, V and VE.
Is the $7,500 exemption automatic?
No. The owner or contractor must submit a written request with a contract or other documents showing the work and its value, and get the city's approval before starting.
Can I split a project to stay under $7,500?
No. Florida Statute 553.79(1)(g) says a project may not be divided into more than one project to evade the permit requirement.
Does the exemption cover condos, duplexes or commercial buildings?
No. It only applies to single-family dwellings. Fort Lauderdale lists condos, multifamily and commercial properties as excluded.
When did the $7,500 permit exemption start?
July 1, 2026. It came from HB 803, signed May 6, 2026 as Chapter 2026-63, Laws of Florida. Fort Lauderdale doesn't accept applications filed before that date.
This article is general information, not legal advice. It reflects section 553.79, Florida Statutes (2026), Chapter 2026-63, Laws of Florida, and the published HB 803 guidance of Fort Lauderdale, Miami, Pompano Beach and Pinecrest as of November 2026. Each building official decides whether a project qualifies, so confirm with yours before any work starts.