Demolition in Miami Beach: Historic Districts, Older Homes and What Has to Be Approved First

In most South Florida cities, tearing down a building starts with a demolition permit. In Miami Beach it can start months earlier, in front of the Historic Preservation Board. Whether that applies to your property depends on one question, and it's worth answering before you buy, design or sign anything.

By Scott Rosenberg, licensed General Contractor

Published All articles

Miami Beach has more than a dozen local historic districts and a long list of individually designated buildings. That's a big part of why the city looks the way it does, and it's also why demolition there works differently. Owners and buyers get caught when they assume a teardown is a simple permit, then find out the building is in a district and the timeline just grew by months. Here's how to tell where you stand and what each path looks like.

First question

Is the property in a historic district?

Local historic districts

Miami Beach has its own local historic districts, set by the city. Buildings inside them are classified as contributing or non-contributing, and both need board approval for total demolition.

Individually designated sites

Some buildings are designated on their own, outside any district. They're treated the same way: total demolition goes to the Historic Preservation Board.

The National Register is separate

The federal National Register of Historic Places is a different list. Being listed there, or not, isn't the same as being in a local district. Check both.

How to check

The city's Planning Department keeps a historic properties database and can tell you a building's district and classification. Ask before you buy or start designing.

Inside a historic district

How demolition approval works

  1. Pre-application meeting

    The first step is a meeting with Planning staff. They'll tell you what the board will want to see and flag problems early.

  2. Application and plans

    You apply for a Certificate of Appropriateness for demolition. For total demolition of a contributing building, the code requires definite plans for the reuse of the property, so the new project has to be designed before the old one can come down.

  3. Staff report

    Planning staff review the request against the city's demolition criteria and write a recommendation to the board.

  4. The hearing

    The Historic Preservation Board hears the request in a public meeting. Neighbors and preservation groups can speak, and the board can approve, deny or add conditions.

  5. Then the permit

    Only after board approval does the demolition move to the Building Department for a permit. A licensed contractor pulls it, and the site is inspected after the work to confirm the building is gone and the property is cleared.

The criteria

What the Historic Preservation Board looks at

What the Historic Preservation Board looks at
ItemQuestionWhat it means
Is it designated?Whether the building is designated historic or contributing, or would reasonably qualify
Could it be rebuilt?Whether the building could only be reproduced with great difficulty or expense
Is it distinctive?Whether it's a distinctive example of a style that contributes to the district's character
Contributing or not?Whether it's classified as a contributing building in its district
Public valueWhether keeping it offers a chance to study local history, architecture and design
Plans for the siteFor total demolition of a contributing building, definite plans for reusing the property
Is it unsafe?Whether the city's Unsafe Structures Board has ordered it demolished

These come from section 118-564 of the Miami Beach Land Development Regulations. The board weighs them together, and the full code has more detail.

Outside the districts

Older single-family homes

Architecturally significant homes

A home built before 1966 may be classified as architecturally significant. According to the city's Planning Department, that classification doesn't change how the home is demolished. It follows the normal demolition permit requirements, with no Design Review Board or Historic Preservation Board review.

Older articles say otherwise

You may read about a special review for homes built before 1942. Rules for older homes have changed over the years, and new proposals to tighten them keep coming up. Check the current rules with the city before you rely on anything you read, including this page.

The new house still gets reviewed

Even when the demolition itself is simple, the home you build next has to meet the city's single-family rules, and some projects go to the Design Review Board.

State law

Florida's Resiliency and Safe Structures Act

What it covers

Passed in 2024, the law limits how much a local government can restrict the demolition of certain buildings on property seaward of the coastal construction control line. It applies when a building doesn't meet federal flood elevation rules for new construction, has been found unsafe, or has been ordered demolished.

What it leaves out

It doesn't apply to single-family homes, buildings individually listed on the National Register, or contributing buildings in National Register districts listed before 2000. Miami Beach's National Register Architectural District was listed in 1979.

What it means for you

It mostly matters for older condo, apartment and hotel buildings near the ocean. Whether a specific building qualifies is a legal question, so talk to a land use attorney before counting on it.

On site

What makes Miami Beach jobs different once the work starts

Tight lots

Many lots are narrow, with neighbors a few feet away. Protection, dust control and careful sequencing matter more than speed.

Waterfront and seawalls

Bayfront and canal lots often have seawalls and docks. Decide early whether they stay, and keep heavy equipment away from them unless an engineer says it's safe.

Asbestos

Commercial and hotel buildings, and apartment or condo buildings with more than four units, need an asbestos survey, and demolition needs a notice before work starts. Smaller homes still benefit from a survey before the crew starts.

Time

Historic Preservation Board applications are generally heard within three to four months, and approvals are valid for 18 months, with extensions of up to one year. Build that into your closing and construction schedule.

Related

Common questions

Frequently asked questions

Do I need approval to demolish a building in a Miami Beach historic district?

Yes. Total demolition of a building in a local historic district, or of an individually designated site, needs approval from the Historic Preservation Board, whether the building is classified as contributing or non-contributing. The demolition permit comes after that approval.

Can I tear down an older house in Miami Beach that isn't in a historic district?

Usually through the normal demolition permit process. According to the city's Planning Department, a home classified as architecturally significant follows the same demolition permit requirements as any other home, with no board review. Confirm the current rules with the city, since they've changed over the years.

How long does Historic Preservation Board approval take?

The city says applications are generally heard within three to four months, starting with a pre-application meeting. Approvals are valid for 18 months and can be extended for up to one year.

Do I need plans for a new building before demolishing a historic building in Miami Beach?

For total demolition of a contributing building, yes. The code requires definite plans for the reuse of the property to be presented to the board.

Does the Resiliency and Safe Structures Act let me demolish my Miami Beach home?

No. The law doesn't apply to single-family homes. It covers certain buildings seaward of the coastal construction control line that don't meet flood elevation rules, have been found unsafe or have been ordered demolished, with exceptions for some historic buildings. Talk to a land use attorney about a specific property.

How do I find out if my property is in a historic district?

Ask the Miami Beach Planning Department. The city keeps a historic properties database that shows a building's district and whether it's classified as contributing.

This article is general information, not legal advice. Historic preservation rules, state law and their interpretation change, and whether a rule applies depends on the specific property. Confirm with the Miami Beach Planning and Building Departments, and talk to a land use attorney before buying or designing around a demolition.

Planning a demolition in Miami Beach?

We'll check what your property needs before you commit, then handle the permit and the work. Get a written quote.

Tell us about the property, what needs to be removed and what comes next.

Request a quote