Most teardown delays we see don't come from the demolition itself. They come from records: a permit a prior owner never closed, an open code case for an unpermitted carport, a fine that kept adding up while the house sat empty. Some of these follow the property, some follow the person, and Florida law treats them differently. The searches are cheap, and the time to run them is before you own the problem.
Once the records are clear, our turnkey demolition service handles the permit, the utility disconnects and the hauling under one contract.
The terms
What is the difference between an open permit, an expired permit and a code lien?
An open permit is a permit that was issued but never finaled. An expired permit is one that lapsed before the work passed inspection. A code lien is a recorded fine for a code violation. The first two are building department records. The third attaches to the land.
Open permit
Issued, but the final inspection never happened or never passed. It can sit open for years, especially when a contractor walked off the job or an owner never called for the final.
Expired permit
A permit that lapsed because work didn't start, stopped too long or never got inspected in time. Under the Florida Building Code, a permit generally becomes invalid if work doesn't begin within six months.
Open code case
A violation that code enforcement cited and that hasn't been fixed, such as an unpermitted addition, an unsafe structure or an overgrown vacant lot.
Code lien
When a code board's fine order is recorded, it becomes a lien. Section 162.09 says it's a lien against the land where the violation exists and against other real and personal property the violator owns.
Florida law
What does Florida law say about open and expired permits?
Since October 1, 2019, section 553.79 of the Florida Statutes has given owners and buyers specific protections and tools for permits left open by someone else. These are the rules as numbered in the 2024 statutes, subsections (16) and (17).
The owner can close it
A property owner can close a permit even if they're not the one listed on the application, by hiring the original contractor, another licensed contractor, or acting as an owner-builder.
Expired but finished work
If a permit expired but the work was substantially completed, the building department can close it without requiring a new permit.
The 6-year rule
A local building department may close a permit 6 years after it was issued, even without a final inspection, if it finds no apparent safety hazards. Note the word may: it's the department's call.
Arm's-length buyers are protected
A department may not deny a building permit to, cite or fine an arm's-length purchaser for value solely because a previous owner's permit was never closed. The department keeps its remedies against the prior owner and the contractor on the permit.
Contractors too
A department may not deny a permit to a contractor solely because that contractor is listed on other permits that were never closed.
Expiration notices
Under section 553.79(1)(c), a local government may send the owner and contractor written notice by email or mail at least 30 days before a permit expires.
Where to look
How do you search for open permits and liens in South Florida?
Start with the folio number. It tells you which government has the records, and each one runs its own search with its own fee.
| Where the property is | What to search | Cost and timing |
|---|---|---|
| City of Miami (folio starts with 01) | What to search: The city's online lien and violation search, by folio number | Cost and timing: $200, paid online, report viewed online after payment |
| Unincorporated Miami-Dade (folio starts with 30) | What to search: The county's Building Permits Search by address or folio, which shows open master permits, inspection holds and what's keeping a permit from closing | Cost and timing: Online |
| City of Doral | What to search: The Building Department's open permit search. Code cases go to Code Compliance and liens to the City Clerk, separately | Cost and timing: $35 per address or folio. Permits Miami-Dade opened before October 1, 2004 show as they do on the county's site |
| Unincorporated Broward | What to search: Building Code Services' property and building code violation research: county permits, code violations and liens | Cost and timing: $50, about 5 to 7 business days by email |
| Unincorporated Palm Beach County | What to search: Planning, Zoning and Building search services: open building permits, fines and liens, open code violations | Cost and timing: $65 for permits or liens, $50 for code violations, 7 to 10 business days. Rush service is $97 or $75 in 3 business days |
| Any other city | What to search: That city's building department for permits, code compliance for open cases, and the city clerk or finance for liens | Cost and timing: Varies by city. Many offer online lien search requests |
Fees and timing are from each government's published search pages as of November 2026. A title company's municipal lien search pulls many of these at once during a closing.
The fix
How do you clear open permits and code liens before demolition?
Sort what you found into permits, code cases and liens, then deal with each one through the office that owns it. Get every resolution in writing.
Sort the list
Separate permits (building department), open code cases (code compliance) and recorded liens (clerk, finance or code board). Each has its own office and its own fix.
Final what's finished
If the work behind an open permit is done, the owner can hire a licensed contractor, or act as owner-builder, to call the final inspection and close it.
Ask about expired permits
If the permit expired but the work was substantially completed, ask the department to close it without a new permit. If it's more than 6 years old with no apparent hazard, ask whether it will close it under the 6-year rule.
Ask how the demolition affects it
When the building with the open permit is the one coming down, ask the reviewer at intake how they want the old permit handled before or with the demolition permit. Departments handle this differently.
Deal with code cases
An open case for an unsafe or unpermitted structure is often resolved by removing it under a demolition permit. Tell code compliance what you're doing and ask what closes the case.
Pay or reduce the liens
Many cities have lien reduction or mitigation applications once the violation is fixed. West Palm Beach and Miami Gardens both publish lien reduction forms. Some cities, like Tamarac and North Bay Village, want liens and pending utility bills cleared before they issue a demolition permit.
Get it in writing
Keep the closed permit record, the case closure letter and the lien satisfaction or release. Your title company, your lender and the next building permit will all ask.
Does it stop the job?
Can an open permit or code lien stop a demolition permit?
An open permit left by a previous owner can't be the sole reason a department denies an arm's-length buyer's permit. But code liens, open code cases and city specific rules can still hold up the job.
If you bought the property
As an arm's-length buyer for value, the department can't deny your permit or fine you solely because a prior owner's permit was never closed. That protection is about inherited permits, not about liens or code cases.
If you pulled the permit
The protection doesn't help the owner or contractor who left the permit open. The department keeps its remedies against them.
City rules on liens
Some cities make lien and bill clearance part of the demolition checklist. Tamarac sends applicants to Utility Billing to clear liens and pending bills, and North Bay Village asks for the same.
Unsafe structure cases
If the city has an unsafe structure case on the building, the demolition may be on a deadline set by the unsafe structures process. That case usually decides the timeline.
From the field
What should a teardown buyer check before closing?
Run the permit, code and lien searches during due diligence, check the older county records for newer cities, and ask the title company for a municipal lien search.
Read the folio first
In Miami-Dade, a folio starting with 01 is the City of Miami and one starting with 30 is unincorporated county. The prefix tells you whose records to pull.
Newer cities have older records elsewhere
For cities formed recently, like Doral in 2003 or West Park in 2005, older permits may live in the county's records. Doral says permits Miami-Dade opened before October 1, 2004 show on the county's site.
Homestead limits foreclosure, not the lien
Section 162.09 says a code lien can't be foreclosed on a homestead, but the lien still sits on the property and usually has to be dealt with at sale.
Unpermitted work on a house you'll keep
If you're keeping the building, unpermitted work is a different job: legalizing it or removing it. Miami-Dade's Code Relief program covers some older work that started before March 1, 2002.
Related
Keep reading
Teardown lot buying guide
Everything to check before you buy a house to knock down.
Removing an unpermitted addition
Legalize it or take it down.
Abandoned and unsafe houses
Unsafe structure cases and deadlines.
Do you need a permit to demolish?
What every demolition permit asks for.
Tear down or flip?
The investor's decision.
Out-of-town owner demolition
Running a teardown from another state.
Common questions
Frequently asked questions
Can I get a demolition permit if the house has open permits?
Usually yes, but expect the building department to ask how the open permits will be handled. If you bought the property at arm's length, section 553.79 says the department can't deny your permit solely because a previous owner's permit was never closed.
Am I responsible for open permits from the previous owner in Florida?
A building department can't deny you a permit, cite you or fine you solely because a prior owner's permit wasn't closed, if you bought at arm's length for value. You can still choose to close it, and the department keeps its remedies against the prior owner and the contractor.
Can a Florida building department close an old permit without a final inspection?
Yes. Under section 553.79, a local building department may close a permit 6 years after issuance, even without a final inspection, if it finds no apparent safety hazards. It's at the department's discretion.
Who can close an open permit in Florida?
The property owner, even if someone else applied for it, by hiring the original contractor, another licensed contractor, or acting as an owner-builder.
Does a code enforcement lien stay with the property in Florida?
Yes. Under section 162.09, a recorded code fine order is a lien against the land where the violation exists, and against other property the violator owns. It can't be foreclosed on a homestead, but it remains on the property.
How much does a lien search cost in Miami?
The City of Miami's online lien and violation search costs $200 and is run by folio number. Folios that don't start with 01 aren't in the City of Miami and need the search from the right city or the county.
How do I check for open permits in unincorporated Palm Beach County?
Through the county's Planning, Zoning and Building search services. An open building permit search is $65 and takes 7 to 10 business days, or $97 for 3-day rush. The ePZB online services also show permit status for non-confidential properties.
Can I reduce a code lien before selling or demolishing?
Often. Many cities accept lien reduction or mitigation applications once the violation is fixed, and demolition can be what fixes it. West Palm Beach and Miami Gardens are two cities that publish lien reduction forms.
This article is general information, not legal advice. It reflects section 553.79, Florida Statutes (subsections (1)(c), (16) and (17) as numbered in the 2024 statutes), section 162.09, Florida Statutes (2026), and the published search pages of the City of Miami, Miami-Dade County, the City of Doral, Broward County and Palm Beach County as of November 2026. For a purchase, talk to your real estate attorney and title company.