Most restaurant demolitions we're asked about fall into one of three situations: a tenant closing who has to hand the space back, a landlord getting a space ready for the next tenant, or an owner tearing down a freestanding building to sell or rebuild. The steps overlap, but who pays for what and who has to sign off is different in each. This guide goes system by system, because that's how the work actually gets done.
We handle restaurant teardowns as part of our commercial demolition work, with the trade subcontractors, permits and disposal paperwork under one contract.
System by system
Who handles each part of a restaurant teardown?
A demolition crew can't legally do all of this alone. Here's who does what, and the paper you should end up with.
| Item | Who does it | Paper to keep |
|---|---|---|
| Grease interceptor or trap | Who does it: A licensed grease waste hauler pumps it out completely. Abandonment or removal goes through the utility and a plumbing permit. | Paper to keep: The hauler's service manifest and the utility's approval |
| Hood fire suppression system | Who does it: A licensed fire equipment company disarms the system and removes the pressurized cylinder | Paper to keep: The company's service report showing the system taken out |
| Walk-in coolers, reach-ins, ice machines | Who does it: An EPA Section 608 certified technician recovers refrigerant from anything that isn't a small appliance | Paper to keep: A recovery record with the technician's name, address and date |
| Gas piping and appliances | Who does it: A licensed plumber or gas contractor caps the lines; the gas utility pulls the meter if the account is closing | Paper to keep: Plumbing permit sign-off and the utility's confirmation |
| Asbestos | Who does it: A licensed asbestos consultant surveys first; a licensed abatement contractor removes anything found | Paper to keep: The survey report and, when required, the county notice |
| Grease duct roof penetration | Who does it: A licensed roofer patches the roof where the duct and exhaust fan come out | Paper to keep: A roofing permit where the city requires one |
| Everything else | Who does it: The demolition crew: ceilings, walls, finishes, quarry tile, equipment, hauling | Paper to keep: Disposal tickets from the landfill or recycler |
Permit requirements vary by city. Commercial interior demolition generally needs a building permit, and work on plumbing, gas, mechanical or fire protection systems may need trade permits of its own.
The grease interceptor
The part of a restaurant teardown that costs landlords the most
The in-ground interceptor out back is where restaurant demolitions most often go wrong, and the rules are written by the county or city utility, not the building department.
Pump it all the way out, with a manifest
Florida DEP now licenses grease waste haulers under Chapter 62-705 of the Florida Administrative Code, and every job needs a service manifest. Have the interceptor pumped completely, not skimmed, before any work near it, and keep the manifest. In Miami-Dade, use a hauler permitted by the county's environmental department (DERM).
Miami-Dade's 12-month clock
Miami-Dade's FOG operating permit is renewed every year and doesn't transfer to a new owner. Under the county code, a space whose permit has been inactive for more than 12 months generally has to meet current FOG code before a new food business gets its Certificate of Use. If the next tenant will be another restaurant, a landlord who lets the device sit unpermitted for a year may be handing that tenant, or themselves, a replacement bill.
Leasing a space with a grease trap? Disclose it
Miami-Dade Ordinance 23-23 created Code section 21-49.2. A seller or landlord of property with a FOG generator has to give the buyer or tenant a signed disclosure on a separate sheet before the deal is signed. Skipping it carries a $1,000 fine and opens the door to a lawsuit.
Don't abandon it on your own
Palm Beach County Water Utilities requires prior written approval for any modification or abandonment of an oil and grease interceptor or trap. Broward cities and Miami-Dade run their own programs, so call the utility that serves the address before anyone fills, cuts or digs out an interceptor.
If the next tenant is a restaurant, leave it alone
A working, properly sized interceptor is worth a lot to the next food tenant. When the space is staying a restaurant, the usual move is to pump it, keep it in service and document its condition, not rip it out.
The kitchen line
Hoods, refrigeration and gas
The hood suppression system is pressurized
The wet chemical system over the cook line is a pressurized cylinder piped to nozzles above the fryers and ranges. A licensed fire equipment company should disarm it and take the cylinder before our crew touches the hood. If the building has a fire alarm tied to that system, tell the monitoring company before it's disconnected.
Clean the grease duct before cutting it
Years of grease coat the inside of the duct. We don't torch-cut a dirty duct. It gets cleaned or cut cold, then lowered in sections, and the exhaust fan comes off the roof.
Refrigerant has to be recovered first
Under EPA's Section 608 rules, refrigeration equipment dismantled on site has to have its refrigerant recovered before disposal, by a certified technician for anything bigger than a small appliance. A small appliance is one sealed at the factory with 5 pounds of refrigerant or less, like many reach-ins and undercounter units. Walk-in coolers and remote condensing units are not small appliances.
Cut lines and 'it leaked out' don't count
The scrap yard or final processor has to get a signed statement that the refrigerant was recovered, with the name, address and date. EPA says refrigerant lost because someone cut the lines doesn't count as having leaked out.
Gas gets capped by a licensed pro
Every appliance connection is shut off and the piping capped by a licensed plumber or gas contractor. If the account is closing, the gas utility removes the meter. Nobody on our crew cuts a gas line on a guess.
Sell the equipment before demo day
Fryers, ranges, walk-in panels and stainless tables have resale value to used restaurant equipment dealers. We don't give scrap or salvage credit on jobs, so sell or move what you want to keep before we start. Whatever is left goes out as debris.
What's under and behind
The surprises restaurant spaces hide
Asbestos rules are stricter than for a house
A restaurant is a commercial facility, so the residential exemption in the federal asbestos rules doesn't apply. The owner or operator has to have the space thoroughly inspected before any demolition or renovation. A demolition always needs a notice 10 working days ahead; a renovation needs one when the regulated asbestos reaches 260 linear feet, 160 square feet or 35 cubic feet. Older floor tile, mastic and pipe insulation are the usual suspects.
Quarry tile on a mortar bed
Commercial kitchen floors are often quarry tile set in a thick mortar bed, sometimes sloped to floor drains. It's heavy, it's slow to remove and it fills containers fast. Ask whether the lease wants the tile out or just the equipment.
Floor drains and trench drains
Every floor sink, trench drain and indirect waste line has to be capped properly, or the next tenant inherits sewer gas and a plumbing problem. That's licensed plumbing work, not a demolition crew with a bag of cement.
Used cooking oil and chemicals
Empty the fryers, have the used oil company pick up its bin, and get the cleaning chemicals off site before we start. They're not demolition debris.
For tenants
How to get the space back to shell and your deposit back
Read the surrender clause first
Leases mean different things by 'shell,' 'vanilla shell' or 'broom clean.' Some want everything out down to the slab; some want the hood, the interceptor and the walk-in left for the next restaurant. Find out before you pay anyone to remove something the landlord wanted to keep.
Get the landlord's scope in writing
Walk the space with the landlord or property manager and get a written list of what stays and what goes. We'll quote from that list.
Send the landlord a certificate of insurance
Most landlords want to be named on the contractor's certificate of insurance before any work starts.
Close the accounts in the right order
Gas and electric are disconnected safely before demolition, not just shut off at the meter, and the FOG permit holder tells the utility the business is closing. In Miami-Dade, the department wants notice on a sale, relocation or transfer of a permitted facility.
Keep every piece of paper
Hauler manifests, the fire equipment company's report, refrigerant recovery records, permit sign-offs and disposal tickets. If the landlord questions the deposit, that file answers them.
Keep reading
Related guides for commercial spaces
The bigger picture
How interior demolition of a commercial space works from start to finish.
Insurance paperwork
What a landlord should see on a certificate of insurance.
Hiring for a commercial job
What to ask before you sign with a demolition contractor.
Related
Keep reading
Commercial interior demolition guide
Taking a commercial space down to the walls.
Commercial demolition cost
What drives the price of a commercial job.
Asbestos and demolition in Florida
Surveys, notices and the commercial rules.
Utilities before demolition
Gas, electric, water and sewer, in the right order.
Common questions
Frequently asked questions
What happens to the grease trap when a restaurant closes in South Florida?
It gets pumped out completely by a licensed grease waste hauler with a service manifest. Whether it stays in service, gets abandoned or comes out depends on the utility and the landlord. Palm Beach County Water Utilities requires written approval before an interceptor is modified or abandoned, and Miami-Dade wants notice when a permitted facility is sold, relocated or transferred.
Does a Miami-Dade FOG permit transfer to a new restaurant owner?
No. The FOG operating permit is renewed every year and is non-transferable, so a new owner needs their own. If the space's permit has been inactive for more than 12 months, the county generally requires the grease device to meet current code before a new Certificate of Use.
Who can remove a restaurant hood fire suppression system?
A licensed fire equipment company should disarm the wet chemical system and remove the pressurized cylinder before the hood is demolished.
Do walk-in coolers need refrigerant recovery before demolition?
Yes. EPA's Section 608 rules require refrigerant to be recovered from refrigeration equipment dismantled on site before disposal, by a certified technician for anything bigger than a small appliance. A walk-in cooler is not a small appliance.
Is an asbestos survey required before demolishing a restaurant?
Yes. A restaurant is a commercial facility, so federal rules require a thorough asbestos inspection before any demolition or renovation, and a demolition needs a notice at least 10 working days before work starts.
Do I have to disclose a grease trap when leasing a restaurant space in Miami-Dade?
Yes. Miami-Dade Code section 21-49.2 requires a seller or landlord to give a signed FOG generator disclosure on a separate sheet before the sale or lease is signed. The fine for skipping it is $1,000.
This article is general information, not legal advice. It reflects Miami-Dade County Code sections 21-49.2 and 24-42.6 and the county's FOG permit rules, Palm Beach County Water Utilities' pretreatment rules, Florida DEP's grease waste rules (Chapter 62-705, F.A.C.), EPA's refrigerant rules (40 CFR Part 82, Subpart F) and asbestos rules (40 CFR 61.145), as of November 2026. Broward County cities set their own grease rules, and every lease is different. Check with the utility, the building department and your landlord before work starts.