Demolition is more than knocking down walls. Pulling the slab, footings, driveway and pool means digging, and the house itself is tied to the ground by electric, gas, water, sewer and communication lines. Florida's Underground Facility Damage Prevention and Safety Act, Chapter 556 of the Florida Statutes, covers all of it. This guide walks through the rules as they apply to a demolition, using the statute and Sunshine 811's own guidance.
Filing the locate ticket and coordinating the utilities is part of every residential demolition job we run.
The rule
What Florida law requires before a demolition
Four parts of Chapter 556 matter most on a demolition job.
2 full business days' notice
The contractor must notify Sunshine 811 not less than 2 full business days before beginning any excavation or demolition. Work under state waters needs 10 full business days.
A ticket lasts 30 days
The information on a locate ticket is valid for 30 calendar days. A demolition that runs longer, or starts late, needs a new ticket.
No demolition until lines are marked or removed
Section 556.105(6)(b) says an excavator may not demolish in the ticket area until the underground facilities are marked and located, or removed. On a teardown, removed usually means the utility has pulled its meter and service line.
Care inside 24 inches
Utilities mark their lines to within 24 inches of the outer edge. Inside that tolerance zone, the contractor has to use increased caution, such as hand digging, soft digging or vacuum excavation, and supervise any machine.
Positive response
Response codes that matter on a demolition
After the ticket goes in, each utility posts a response code. The contractor checks every code against what's painted on the ground before anything comes down.
| Code | What the utility is saying | What happens next |
|---|---|---|
| 1, Marked | What the utility is saying: The utility's lines are marked within the ticket area. | What happens next: Work around the marks and respect the 24-inch tolerance zone. |
| 4, Clear | What the utility is saying: The utility has no facilities at the site. | What happens next: Nothing to mark for that utility. |
| 5, No conflict | What the utility is saying: The utility has lines nearby, but outside the described or white-lined area. | What happens next: Stay inside the area you described. |
| 6A, Active facilities present | What the utility is saying: For demolition work, the utility has active facilities in the area. | What happens next: Don't demolish until the utility notifies you the site is clear, usually after its service is disconnected and removed. |
| 8, Ongoing job | What the utility is saying: The locator and the contractor have agreed on a marking schedule. | What happens next: Follow the agreed schedule on longer jobs. |
| 3 series, Unmarked | What the utility is saying: The site wasn't marked, often because of blocked access or unclear directions. | What happens next: Call the utility before any digging or demolition. |
From Sunshine 811's published response codes. If a code and the marks on the ground don't match, the contractor contacts that utility before working.
On a real job
How 811 fits into a South Florida demolition
This is the order we follow on a typical house demolition.
Request disconnects first
Electric, gas, water and sewer are disconnected and capped by the utilities and a plumber before demolition. Those letters come before the permit, and they're also how a 6A response gets cleared.
File the ticket with the right area
The contractor files with the address, the work area, the start date, whether machinery is used and how deep the work goes. Marking the area in white paint or flags helps the locators see exactly where the work is.
Wait two full business days
A ticket filed Friday afternoon isn't ready Monday morning. Weekends, holidays and the day of the call don't count.
Check every response
Compare each utility's code with the paint and flags on the ground. A missing response or marks that don't match means a call to that utility, not a guess.
Find the private lines
811 doesn't mark lines the property owner owns. Before the slab and footings come out, the sewer lateral, irrigation, pool lines and any power run to a shed or gate have to be found another way.
Dig carefully near the marks
Footings, slabs and driveways near a marked line come out by hand or with careful machine work inside the 24-inch zone.
Renew if the job runs long
If the job passes 30 days, or the marks wear off, the contractor files again before more digging.
Reading the marks
What the paint colors mean
Locators use the national APWA color code. These are the colors you'll see on a South Florida lot.
| Color | What's underneath |
|---|---|
| Red | What's underneath: Electric power lines, cables and conduit |
| Yellow | What's underneath: Gas, oil, steam or other flammable material |
| Orange | What's underneath: Communications: phone, cable TV, fiber, alarm lines |
| Blue | What's underneath: Drinking water |
| Purple | What's underneath: Reclaimed water, irrigation and slurry lines |
| Green | What's underneath: Sewer and drain lines |
| White | What's underneath: The proposed excavation or demolition area |
| Pink | What's underneath: Temporary survey markings |
APWA Uniform Color Code, used by Sunshine 811 member utilities.
What 811 won't do
Lines that won't be marked
Member utilities mark only what they own. On a typical South Florida lot, that leaves a lot underground.
The sewer lateral
The pipe from the house to the city main or the septic tank usually belongs to the owner, and it's the line that has to be capped before demolition.
Irrigation and pool lines
Sprinkler lines, pool plumbing and pool electrical are almost always private, and they run right where slab and deck removal happens.
Power to outbuildings
A line run to a detached garage, shed, gate, lamp post or dock is the owner's, not FPL's.
Old abandoned lines
Older houses can have abandoned septic tanks, old wells and lines nobody remembers. They're one reason demolition contracts carry an allowance for hidden conditions.
If something goes wrong
Hitting a line and what it costs
Chapter 556 has penalties, and a damaged line is usually expensive before any fine is counted.
Stop and call
If a line is hit, stop work and notify the utility using the contact on the ticket. If gas or another hazardous material is released, call 911 and get everyone away.
$500 and up
Sunshine 811 lists noncriminal penalties of $500 plus court costs for violations such as excavating in the tolerance zone without increased caution, and $2,500 when the line carries hazardous materials regulated by federal pipeline rules.
Up to $50,000
Incidents causing death or serious injury, more than $50,000 in damage, or an outage for 2,500 or more customers can bring penalties up to $50,000, and the State Fire Marshal decides whether to investigate.
Don't move the marks
Knowingly removing or destroying valid stakes, paint or markers that identify underground lines is a second-degree misdemeanor.
Related
Keep reading
Common questions
Frequently asked questions
Do you have to call 811 before demolishing a house in Florida?
Yes. Florida Statutes 556.105 requires the excavator to notify Sunshine 811 at least 2 full business days before beginning any excavation or demolition. On a demolition, the contractor files the ticket, and it may not demolish in the area until the underground facilities are marked and located or removed.
Who calls 811, the homeowner or the contractor?
The law puts the duty on the excavator, the person or company doing the work. On a demolition you've hired out, that's your contractor. Ask for the ticket number before work starts.
How long is a Sunshine 811 ticket good for?
30 calendar days. If the demolition starts late or runs longer, the contractor needs a new ticket.
What does response code 6A mean?
For demolition work, 6A means the utility has active facilities in the area. Sunshine 811's guidance is not to demolish until that utility notifies you the site is clear, which usually follows the disconnect and removal of its service.
Will 811 mark my sewer line and sprinkler lines?
Usually not. Member utilities only mark the lines they own. The sewer lateral from the house, irrigation, pool lines and power to sheds or gates are typically private and have to be located another way.
What colors do the utility marks use?
Red is electric, yellow is gas, orange is communications, blue is drinking water, purple is reclaimed water and irrigation, green is sewer, white marks the proposed work area and pink is temporary survey marking.
This is general information, not legal advice. It reflects Chapter 556 of the Florida Statutes and Sunshine 811's published guidance as of November 2026. Penalties and procedures can change, so check sunshine811.com and the current statute before you rely on them.