Skip to main content
Rosemont Ventures Group home
ROSEMONTVentures Group LLC
Español
The Teardown

15 Local Demolition Rules That Surprise South Florida Property Owners, City by City

Most people expect a demolition permit to work the same way everywhere in South Florida. The county pieces do: the asbestos notice, the sewer cap, the utility letters. But each city adds its own rules on top, and those are the ones that cost owners a week, a fine or a second dumpster. These are the ones we ran into while rebuilding our city pages this month, each taken from the city's own checklist, code or permit page.

By Scott "Schneur" Rosenberg, Florida certified general contractor (CGC1541479)

Published All articles

Over the past few weeks we rewrote the permit section of every city page on this site, using each city's own documents instead of a county template. Along the way we kept finding rules that most owners, and plenty of contractors, have never heard of. Here are fifteen of them, grouped by what they affect, with a link to the city page that has the details.

Knowing these rules before we price a job is part of how our turnkey demolition service keeps permits from stalling.

At a glance

The rules, city by city

Each of these comes from the city's own checklist, code or permit page as published in November 2026.

The rules, city by city
CityThe ruleWhy it matters
MiramarThe rule: All demolition debris must be removed by Waste Pro of Florida (City Code Sec. 18-7), with a notarized debris removal affidavit on the permit.Why it matters: Any other dumpster company is a code violation.
Pembroke PinesThe rule: Waste Pro holds the exclusive C&D franchise, and the city offers a 60-day early start agreement before the permit is issued.Why it matters: Your hauler choice is made for you, and work can start sooner on big jobs.
West Palm BeachThe rule: Every demolition application goes to Historic Preservation, every demo needs a stormwater plan (SWPPP), and the lot is finished graded to the sidewalk, seeded and mulched.Why it matters: Even a plain 1970s house goes through historic review.
Golden BeachThe rule: Demolition only from 8 AM to 6 PM on weekdays, never on weekends or six holidays (Town Code Sec. 14-84); the street is swept twice a day.Why it matters: The same teardown takes more calendar days here.
MedleyThe rule: The Building Department works Monday through Thursday and is closed on Fridays.Why it matters: A Friday signature or pickup waits until Monday.
Coral GablesThe rule: A Historical Significance Determination letter is posted online, anyone can appeal it for 10 days, and it expires after 18 months. The city also asks for a bat check before demolition.Why it matters: Plan for the appeal window before you schedule the crew.
Hialeah GardensThe rule: Every signature on the application is notarized, the insurance certificate is made out to the city, and every permit needs an HOA affidavit.Why it matters: A missing notary stamp sends the package back.
Bal HarbourThe rule: Applications are taken in person only, and plans are reviewed on set days of the week.Why it matters: Missing a review day can cost a week.
Miami BeachThe rule: The residential demolition checklist wants elevations in NGVD, a tree survey, a dust control letter and DERM asbestos review when there are two or more structures.Why it matters: More surveying and paperwork than most cities ask for.
Boca RatonThe rule: A 1% deposit (minimum $100) at application, a letter to the neighbors, and separate disconnect letters from FPL and FPU.Why it matters: Electric and gas are two different companies here.
North MiamiThe rule: A flat $325 per structure for complete demolition, including the trade sub-permits, plus a fence permit at $0.45 per linear foot.Why it matters: One of the few cities that publishes the number.
HollywoodThe rule: Every C&D hauler needs a yearly city permit from Public Works, and construction noise is limited to set hours, with no work on Sundays.Why it matters: Ask the dumpster company for its Hollywood permit.
Delray BeachThe rule: C&D roll-offs need a city franchise hauler, can only sit on a property with an active building permit and can never go in the right of way.Why it matters: No dumpster in the street, even for a day.
DoralThe rule: Paper submittals add two to three business days for scanning, and the temporary fence needs its own fence and dust screen sub-permit.Why it matters: Apply online and add the fence to the plan.
AventuraThe rule: Inspections are requested online only; the city stopped taking them by phone in 2016. Construction runs 7 AM to 6 PM weekdays and 8 AM to 5 PM Saturdays.Why it matters: Condo associations often set even shorter hours.

Rules, fees and hours change. Confirm the current rule with the city before you rely on it. Each city's page on this site lists the source.

Who hauls the debris

Cities that decide your dumpster company

The rule that catches the most people, because breaking it is easy and the fine can land on the owner.

Miramar

Only Waste Pro of Florida may remove demolition debris, under City Code Section 18-7. The permit package includes a notarized Construction Debris Removal Affidavit, so the hauler is on record before work starts.

Pembroke Pines

Waste Pro holds the exclusive franchise for construction and demolition debris. A contractor can use containers it owns, but hiring a third-party hauler isn't allowed, and the city says owners may be held responsible.

Hollywood and Delray Beach

Hollywood requires a yearly Public Works permit for every C&D hauler. Delray Beach requires a franchise and keeps roll-offs out of the right of way entirely.

When the crew can work

Hours, days and office schedules

A short workday or a closed office doesn't sound like much until it adds a week to the job.

Golden Beach

Demolition is allowed only from 8 AM to 6 PM on weekdays, with no work on Saturdays, Sundays or six holidays, and the gates can't open before 8. The street has to be swept at least twice a day.

Medley

The Town of Medley Building Department keeps a four-day week, Monday through Thursday, and closes on Fridays. Plan signatures and pickups early in the week.

Coral Gables and Aventura

Coral Gables allows construction from 7:30 AM to 6 PM on weekdays, restricts exterior work in residential areas on Saturdays and bans Sundays and holidays, including December 24. Aventura allows 8 AM to 5 PM on Saturdays.

Paperwork

Signatures, reviews and the order things happen

Most delays come from paperwork, not from the demolition itself.

West Palm Beach

The city's checklist sends every demolition application to the Historic Preservation office on the second floor of City Hall, not just ones in historic districts, and requires a stormwater pollution prevention plan on every demolition.

Coral Gables

A building that isn't historically designated still needs a Historical Significance Determination letter. It's posted online, any citizen can appeal within 10 days, and it expires if the demolition permit isn't issued within 18 months.

Hialeah Gardens

Every signature on the permit application has to be notarized, the contractor files an insurance certificate made out to the city, and every permit carries an HOA affidavit, HOA or not.

Bal Harbour

The village takes applications at the counter only. Building trades review plans Monday through Thursday, and Public Works, Utilities and Zoning on Tuesdays and Thursdays.

Money

Deposits and fees that are spelled out

Most cities don't publish a demolition fee you can plan around. These do.

North Miami

Complete demolition is $325 per structure under the city's fee schedule, including the mechanical, electrical and plumbing sub-permits. A screened construction fence is a separate permit at $0.45 per linear foot, with a $120 minimum.

Boca Raton

Boca collects 1% of the contract value (minimum $100) when you apply, with the rest due at issuance, and requires a recorded Notice of Commencement on jobs over $5,000.

Pembroke Pines

The pre-permit early start agreement lets work begin after one full review cycle, for a fee. It expires after 60 days with no extensions, and the permit has to follow within 30 days.

Environment and history

Trees, floods, bats and old buildings

Some cities look harder at what's around the building than at the building itself.

Miami Beach

The residential checklist asks for elevations in NGVD, a tree survey and Urban Forestry tree permit when trees are affected, a dust control letter, and DERM asbestos review when the site has two or more structures. The city has 14 local historic districts.

Coral Gables

The city asks that buildings, attics and roofs be checked for endangered bats before demolition. If roosting bats turn up, work stops and the U.S. Fish and Wildlife Service is called.

West Palm Beach

When the building is gone, the lot has to be graded to the level of the sidewalk, then seeded and mulched before the permit closes.

Related

Common questions

Frequently asked questions

Are demolition rules the same in every South Florida city?

No. The county rules for asbestos notices, sewer caps and environmental review apply everywhere in each county, but each city adds its own. Miramar decides who hauls your debris, Golden Beach limits demolition to weekdays, West Palm Beach sends every demolition to historic review, and Hialeah Gardens requires every signature to be notarized.

Which South Florida cities control who can haul demolition debris?

Miramar and Pembroke Pines allow only Waste Pro. Plantation, Margate, Boca Raton and Delray Beach allow only franchised haulers, Coral Springs keeps an approved list for homes, and Hollywood requires a yearly city permit for every construction and demolition hauler.

Can you demolish a house on a weekend in South Florida?

It depends on the city. Golden Beach bans demolition on Saturdays, Sundays and six holidays. Coral Gables bans Sundays and restricts exterior work in residential areas on Saturdays. Aventura allows Saturday work from 8 AM to 5 PM. Check your city's noise and construction hours before you schedule.

Does every demolition in West Palm Beach need historic approval?

The city's demolition checklist sends every demolition application to the Historic Preservation office for approval, not only buildings in historic districts. Plan for that step even if the house isn't historic.

How much is a demolition permit in South Florida?

Most cities base the fee on the job's value and don't publish a flat number. North Miami's fee schedule lists $325 per structure for complete demolition, and Boca Raton collects 1% of the contract value (minimum $100) at application. County fees, the asbestos survey and the utility letters are separate.

Rules, fees, office hours and hauler franchises change. This roundup reflects each city's published checklist, code or permit page as of November 2026. Confirm the current requirements with the city's building department before you rely on them.

Not sure what your city requires?

We check your city's own rules before we price the job, so the permit doesn't stall and the dumpster is the right one.

Tell us about the property, what needs to be removed and what comes next.

Request a quote