This guide covers what happens to sewer and septic when you tear down and rebuild, using Florida law, Miami-Dade's Chapter 24 and its septic guidance manual, and city rules in Fort Lauderdale and Coral Gables. It's written for owners, buyers and builders planning a teardown on a lot that's on septic today. For the demolition side (capping the sewer or abandoning the tank before the house comes down), we have a separate guide.
When we quote a house demolition on a septic lot, we include the tank abandonment and flag the sewer question early, because it shapes the site plan for the new house.
Three outcomes
Where your lot lands
Sewer is in your street: connect
If a public gravity sewer or force main is in the right-of-way or easement next to your lot, a new house connects to it. Miami-Dade bars installing or replacing a septic system when sewer is available in an abutting right-of-way or easement, and Fort Lauderdale's code says no septic tank may be built where a city sewer is available.
Sewer is nearby: you may have to extend it
In Miami-Dade, sewer doesn't have to touch your lot. If the nearest connection point is within the county's feasible distance, the new house has to extend the line and connect instead of using septic. This is the outcome that surprises people, because the cost of the extension usually lands on the project.
Sewer is out of reach: a new septic system
If there is no sewer within reach, the new house can use an onsite system. In Miami-Dade it has to meet today's rules: no conventional systems, DERM review, a minimum lot size and enough separation from the water table. In Broward and Palm Beach, the state's septic rules apply, along with any city rules.
The rules, place by place
When a rebuild has to connect to sewer
What each source says, checked in November 2026.
| Item | When you must connect | Septic for the new house | Where it comes from |
|---|---|---|---|
| Florida (statewide) | When you must connect: A working septic system must connect within 365 days after written notice that sewer is available. A system that needs repair must connect within 90 days of the state's notice. | Septic for the new house: For a single-family home, sewer counts as available when a line sits in a public easement or right-of-way abutting the property and has capacity. | Where it comes from: Sections 381.00655 and 381.0065, Florida Statutes |
| Miami-Dade County | When you must connect: When sewer is in an abutting right-of-way or easement, or within the feasible distance of your lot. | Septic for the new house: Only beyond feasible distance. New and fully replaced systems need DERM review (since January 1, 2023), and conventional systems are no longer allowed. | Where it comes from: Chapter 24 (Secs. 24-43.1 and 24-43.4), Ordinance 22-83, DERM's septic guidance manual |
| Fort Lauderdale | When you must connect: Owners of lots on a street with a sewer line must connect within 90 days of the completion date certified by the city engineer. | Septic for the new house: No new septic tank where a city sewer is available. | Where it comes from: City Code Chapter 28 (Secs. 28-32 and 28-33) |
| Coral Gables | When you must connect: No city mandate. The city says you have to connect under state or county law only if sewer is installed on your street. | Septic for the new house: Yes, where no sewer is available, under Miami-Dade's rules. A failing tank has to be replaced with a more advanced system. | Where it comes from: City of Coral Gables septic to sewer program page |
| Elsewhere in Broward and Palm Beach | When you must connect: The state rule applies, and many cities add their own connection rules in their utility codes. | Septic for the new house: Where sewer isn't available, under the state onsite sewage program and any local rules. | Where it comes from: Your city or county utility |
This is a summary. Utilities apply these rules lot by lot, so get a written answer from the utility for your address before you design the new house.
Miami-Dade
The feasible distance rule, and why a bigger house changes it
How the county measures it
For residential uses on a gravity sewer, Chapter 24 requires the extension when the distance to the nearest available connection point is less than the building's gross floor area divided by 20. A gravity connection point within 100 feet triggers it no matter the size. DERM decides where the nearest connection point is.
A worked example
The old 1,600 square foot house: 1,600 divided by 20 is 80 feet, so the 100 foot minimum controls. The new 3,000 square foot house: 150 feet. A 4,500 square foot house: 225 feet. The same lot, with the same sewer down the block, can go from "septic is fine" to "extend the sewer" just because the new house is bigger.
Small additions are treated differently
The county doesn't require a sewer extension for an addition or remodel under 25% of the existing floor area. A teardown is new construction, so it's measured on the full new building.
Other uses have longer distances
The same definition sets longer automatic distances for other uses: 300 feet for office, 500 feet for business districts and 700 feet for industrial, along with floor area formulas. If you're replacing a house with something other than a house, ask DERM which test applies.
If you stay on septic
What a new septic system has to meet in Miami-Dade
No conventional systems
Under the guidance that took effect January 1, 2023, the old conventional system (Type 1) isn't allowed for a new system or a full replacement. The new system has to meet at least secondary treatment standards, and DERM decides which type a site needs.
DERM review
Ordinance 22-83, adopted July 7, 2022, added DERM review of new and fully replaced septic systems. A new house on a lot beyond feasible distance goes through it.
Minimum lot size
The guidance lists 15,000 square feet for a single-family home on public water and 20,328 square feet without public water. Duplexes need more. If your lot is smaller, raise it with DERM before you design, because it can decide the whole project.
Water table separation
The bottom of the drainfield has to be at least 36 inches above the wet season high water table, using the higher of the site's own indicators or DERM's maps. On low lots this is often what forces a raised (mound) drainfield.
Setbacks
Chapter 24 keeps a drainfield 100 feet from surface water, such as a canal, lake or the bay, and 100 feet from a drinking water well. Waterfront lots can run out of room fast.
The sequence
How a teardown goes from septic to sewer
Ask the utility before you design
Get a written answer on whether sewer is available for your address, where the nearest connection point is and whether there's capacity. In Miami-Dade, that's WASD and DERM. In cities with their own utility, it's the city.
Abandon the tank during demolition
The old septic tank is pumped out and abandoned under a permit, usually as part of the demolition. Our sewer cap and septic guide covers how that works.
Get the sewer allocation
In Miami-Dade, a new connection or a change in use needs a sewage flow allocation, and the utility checks the main and the lot's frontage. Larger projects may also need a capacity certification.
Permit the lateral and any extension
The new house needs a plumbing permit for its sewer lateral. If the line has to be extended, that's an engineered sewer extension with its own permit and work in the right-of-way.
Pay the connection charges and connect
The utility sets the connection charges for your project. In Miami-Dade, WASD calculates them at the time of the request based on expected use.
Expect the sewer bill
Under Miami-Dade Code Sec. 32-79, sewer billing starts 90 days after the connection charges are paid.
Money
Costs to price before you buy or design
Connection and capacity fees
These vary by utility. Fort Lauderdale's capital expansion fee schedule (revised January 2025) lists $651 per equivalent residential connection for wastewater, with one connection equal to 300 gallons a day. Miami-Dade calculates its charges per request. Ask the utility for the exact figure for your project.
The lateral and street work
A new lateral from the house to the main, and any tap or work in the street, are part of the rebuild's site work. A deeper or longer run costs more, so the house's position on the lot matters.
A sewer extension
If Miami-Dade's feasible distance rule applies, extending the line is often the biggest sewer cost on the job. It needs design, permits and right-of-way work, so get it priced before you commit to a house size.
Or a new septic system
A treatment system with DERM review, and possibly a mound, costs more than the conventional tank the old house had. Compare that number against the sewer option, not against the old system.
Assistance programs
Miami-Dade offers up to $15,000 in grants or loans to homestead owners converting an existing septic system where sewer is already available. It's built for occupied homes, so a teardown may not qualify; call 786-268-5111 to ask. Under state law, owners notified that sewer is coming can prepay connection charges in monthly installments over up to 2 years.
Why it matters now
South Florida is moving off septic
Miami-Dade
The county counts about 120,000 septic systems and estimates that about 9,000 are already vulnerable to rising groundwater, growing to about 13,500 by 2040. Through its Connect 2 Protect program it is extending sewer to commercial corridors and neighborhoods.
Coral Gables
The city has mapped 19 proposed sewer basins, ranked by risks like septic failure, flooding and closeness to water, and is studying a voluntary co-op to help owners get contractor pricing.
Hollywood
In the November flood, CBS Miami reported septic backups mixed with floodwater in Playland Estates, a neighborhood with no sewer. It's a reminder that on a low lot, the septic question is about more than the permit.
Florida law
The state's 365-day and 90-day connection rules apply everywhere once a utility gives written notice that sewer is available.
Related
Keep reading
Sewer caps and septic tanks before demolition
How the old connection is sealed or the tank abandoned.
Buying a teardown lot
What to check before you buy a house to knock down.
Trees on a teardown lot
Another site rule that shapes where the new house can go.
Demolition permit fees
What South Florida building departments charge.
Common questions
Frequently asked questions
Can my new house use the old septic tank?
Usually not. In Miami-Dade, a new house beyond feasible distance needs a new system that meets current standards and goes through DERM review, and conventional systems are no longer allowed for new or fully replaced systems. If sewer is available, the old tank is abandoned and the new house connects.
Sewer is on my street. Do I have to connect when I rebuild?
Yes. Miami-Dade doesn't allow a septic system to be installed or replaced when sewer is available in an abutting right-of-way or easement, and Fort Lauderdale's code bars new septic tanks where a city sewer is available. State law also requires connection once the utility gives written notice.
Sewer is down the block, not in front of my lot. Am I off the hook?
Not necessarily, in Miami-Dade. If the nearest connection point is within the county's feasible distance, you have to extend the sewer. For a house on a gravity sewer, that's anything within 100 feet, or within the new building's floor area divided by 20, whichever is greater. A 3,000 square foot house works out to 150 feet.
How do I find out if sewer is available for my lot?
Ask the utility that serves the address for a written answer, before you design the new house. In Miami-Dade, that's the Water and Sewer Department, with DERM reviewing septic and feasible distance questions. Many Broward and Palm Beach cities run their own utilities.
How long do I have to connect after sewer is installed?
Under state law, 365 days after written notice for a working septic system, or 90 days after the state's notice if the system needs repair. Fort Lauderdale's code gives 90 days from the completion date certified by the city engineer.
Does Miami-Dade's $15,000 septic to sewer assistance cover a teardown?
Probably not as written. The program is for homestead owners converting an existing septic system where sewer is already available, and investment and non-residential properties are excluded. The county's page doesn't address new construction, so call 786-268-5111 to ask about your case.
Does Coral Gables require me to convert to sewer?
The city says there's no city mandate. You have to connect under state or county law only if a sanitary sewer is installed on your street. If your septic system fails, county law requires replacing it with a more advanced system.
Who handles the old septic tank during demolition?
The tank is pumped and abandoned under a permit, normally as part of the demolition, and the demolition contractor coordinates it. Our guide to sewer caps and septic abandonment covers the details.
This article is general information, not legal or engineering advice. It reflects Sections 381.00655 and 381.0065 of the Florida Statutes, Miami-Dade County Code Chapter 24 and DERM's septic (OSTDS) guidance manual, Ordinance 22-83, Miami-Dade Code Sec. 32-79, the Miami-Dade Water and Sewer Department's septic to sewer assistance page, Fort Lauderdale City Code Chapter 28 and its capital expansion fee schedule (Rev. 3, January 2025), the City of Coral Gables septic to sewer program page and CBS Miami's November 2026 flood reporting, as checked in November 2026. Rules and fees change, and utilities decide availability lot by lot, so get a written answer from your utility before you design. Planning a teardown on a septic lot? Send us the address. We'll include the tank abandonment in a written quote and tell you what to ask the utility.