Boca's checklist is unusually complete: almost everything the city will ask for is listed on a single page. This guide walks through that list in plain terms and adds the county steps that apply on top of it. It's based on the city's Demo Entire Building checklist and the city's permitting pages as they read in November 2026. The city can change its forms, so check the current checklist before you file.
If you'd rather hand the whole list off, our residential demolition service covers the Boca permit, the disconnects and the cleanup under one contract.
The city's list
What's on Boca Raton's demolition checklist
This is the Demo Entire Building checklist from Boca Raton's Development Services, Building Administration, grouped the way the city lists it.
Forms
- Submittal form
- Building application
- Environmental application
- Electrical application
- Authorized agent form
- Demo form
- Water and sewer form
Documents from the contractor or owner-builder
- The contract
- An adjacent owner notification letter
- An FPU disconnect letter
- An FPL disconnect letter
- A refrigerant affidavit
- The recorded warranty deed
- A site plan and survey
- A propane gas affidavit
- A demolition letter to the building official
Owner-builders also need
- An owner-builder affidavit
- An estimate of costs
Fees and timing
- A deposit of 1% of the contract value, with a $100 minimum, due up front; the balance is due when the permit is issued
- All subcontractor applications filed before the permit is issued
- A certified Notice of Commencement when the building permit value is over $5,000
Who you'll deal with
The offices and companies involved in a Boca demolition
The permit is the city's, but several other offices and utilities have to sign off before it's issued.
| Who | What they handle |
|---|---|
| Boca Raton Development Services, Building Administration | What they handle: The demolition permit, the review and the inspections. Applications go through the city's Boca eHub portal. |
| FPL | What they handle: The electric disconnect letter. |
| FPU (Florida Public Utilities) | What they handle: The gas disconnect letter. |
| Water and sewer | What they handle: The water and sewer form in the permit package. If the house is on septic instead of sewer, the tank has to be abandoned under a separate permit. |
| Your AC or mechanical contractor | What they handle: Recovering the refrigerant, which backs the refrigerant affidavit. |
| Florida Department of Health in Palm Beach County | What they handle: Asbestos for commercial buildings and buildings with five or more units: a survey, a notice at least 10 working days ahead, the fee and written approval before work starts. |
The order
How to move a Boca Raton demolition permit along
The disconnect letters and the neighbor letter take the longest, so they go first.
Confirm who's pulling the permit
Boca says every contractor has to be registered with the city and up to date to pull permits. If you're pulling it yourself as an owner-builder, you'll need the owner-builder affidavit and a cost estimate.
Request the disconnects
Ask FPL and FPU for their disconnect letters as soon as you decide to demolish. Utility letters are usually the slowest part of any demolition permit.
Handle the refrigerant and the propane
Have the AC refrigerant recovered so the refrigerant affidavit can be signed, and sort out any propane tank on the property for the propane gas affidavit.
Notify the neighbors and gather the paperwork
Prepare the adjacent owner notification letter, the recorded warranty deed, the site plan and survey, the contract and the demolition letter to the building official.
File online and pay the deposit
Submit the forms and documents through Boca eHub, pay the 1% deposit, and make sure every subcontractor's application is in before issuance. Record the Notice of Commencement if the value is over $5,000.
Worth knowing
What catches people off guard in Boca
Most of these are easy once you know about them, and slow if you find out at the counter.
The neighbors get a letter
The checklist requires an adjacent owner notification letter with the application. It's a good moment to talk to the neighbors about the schedule, dust and parking too.
Two separate utility letters
Electric and gas come from different companies here: FPL for power and FPU for gas. Each one sends its own disconnect letter.
Money due before review
The 1% deposit, with a $100 minimum, is due when you apply, not when the permit is issued. The rest is due at issuance.
Old fuel tanks have their own checklist
Boca keeps a separate underground fuel tank removal checklist. If the property ever had a fuel tank, plan for it before the demolition.
Commercial buildings add the county asbestos steps
For commercial buildings and buildings with five or more units, the Department of Health's survey, notice and written approval come before demolition.
Pulling it yourself
Demolishing your own house in Boca as an owner-builder
Boca allows owner-builders, with extra paperwork.
Two extra documents
The checklist adds an owner-builder affidavit and an estimate of costs to the regular list.
The same responsibilities
As the permit holder, you take on what a contractor normally carries: the inspections, the site safety and anyone working for you.
Insurance still matters
If you hire anyone to run equipment or haul debris, ask for their certificate of insurance before they start.
Related
Keep reading
Palm Beach County demolition permits
The county rules, the Health Department asbestos program and what other cities add.
Demolition in Palm Beach County
Every Palm Beach city we serve, and what's different about demolition there.
Utilities before demolition
Disconnect letters, the sewer cap or septic, and what holds them up.
Beachfront demolition and the CCCL
Extra state rules for properties seaward of the coastal construction line.
Common questions
Frequently asked questions
Do I need a permit to demolish a house in Boca Raton?
Yes. Demolishing a building in Boca Raton needs a permit from the city's Development Services, Building Administration, using the city's Demo Entire Building checklist. Applications are filed online through Boca eHub.
What documents does Boca Raton require for a demolition permit?
The checklist lists seven forms (submittal, building, environmental, electrical, authorized agent, demo and water and sewer) plus the contract, an adjacent owner notification letter, FPU and FPL disconnect letters, a refrigerant affidavit, the recorded warranty deed, a site plan and survey, a propane gas affidavit and a demolition letter to the building official.
How much is the deposit for a demolition permit in Boca Raton?
The checklist says 1% of the contract value is due up front, with a minimum of $100, and the remaining balance is due when the permit is issued.
Do I need a Notice of Commencement for a demolition in Boca?
Boca requires a certified Notice of Commencement on building permits with a value greater than $5,000.
Can a homeowner pull a demolition permit in Boca Raton?
Yes, as an owner-builder. The checklist adds an owner-builder affidavit and an estimate of costs. Contractors pulling the permit have to be registered with the city and up to date.
Do I need to notify my neighbors before demolishing in Boca Raton?
Yes. An adjacent owner notification letter is one of the documents on the city's demolition checklist.
Based on the City of Boca Raton's Demo Entire Building checklist and the city's permitting pages, plus Palm Beach County asbestos rules, as they read in November 2026. Forms, fees and requirements change, so confirm with Boca Raton Development Services at (561) 393-7930 before you file. This is general information, not legal advice.