These are the hours each city publishes for construction noise, which is what demolition falls under. Some towns add their own demolition rules on top, and a condo association or HOA can set shorter hours that also apply. Every row links back to the official page or code section so you can check it before you schedule a crew.
When we schedule a house demolition, we plan the loud work, the trucks and the deliveries around the city's hours and any building or HOA rules.
City by city
Construction and demolition hours in South Florida
Hours as each city publishes them, checked in November 2026.
| Item | Weekdays | Saturday | Sunday and holidays |
|---|---|---|---|
| City of Miami | Weekdays: 8 a.m. to 6 p.m. | Saturday: 8 a.m. to 6 p.m. | Sunday and holidays: Noise waiver required on Sundays and federal holidays |
| Miami Beach (residential zones) | Weekdays: 8 a.m. to 6 p.m. | Saturday: 10 a.m. to 4 p.m. | Sunday and holidays: No construction noise |
| Miami Beach (commercial and mixed-use zones) | Weekdays: 7:30 a.m. to 6:30 p.m. (7:30 p.m. in daylight saving time) | Saturday: Same as weekdays | Sunday and holidays: No construction noise |
| Coral Gables | Weekdays: 7:30 a.m. to 6 p.m. | Saturday: 9 a.m. to 5 p.m. for interior work; exterior residential work only in limited cases | Sunday and holidays: No construction, including December 24 |
| Aventura | Weekdays: 7 a.m. to 6 p.m. | Saturday: 8 a.m. to 5 p.m. | Sunday and holidays: Only with City Manager approval |
| Bay Harbor Islands | Weekdays: 9 a.m. to 6 p.m. | Saturday: No construction | Sunday and holidays: No construction; town holidays include the day after Thanksgiving and December 24 |
| Golden Beach (demolition) | Weekdays: 8 a.m. to 6 p.m. | Saturday: No demolition | Sunday and holidays: No demolition on Sundays or six named holidays |
| Hollywood | Weekdays: 7 a.m. to 6 p.m. | Saturday: 8 a.m. to 6 p.m. | Sunday and holidays: No Sunday demolition without the Chief Building Official's written approval |
| Fort Lauderdale | Weekdays: 8 a.m. to 7 p.m. | Saturday: 8 a.m. to 7 p.m. | Sunday and holidays: Sundays 10 a.m. to 7 p.m. |
| West Palm Beach | Weekdays: 7 a.m. to 7 p.m. | Saturday: 8 a.m. to 8 p.m. | Sunday and holidays: Sundays 8 a.m. to 8 p.m. |
| Town of Palm Beach (Nov. 1 to Apr. 30) | Weekdays: 9 a.m. to 5 p.m. | Saturday: No construction | Sunday and holidays: No construction on Sundays or town holidays |
Hours apply to construction noise generally, including demolition. Condo associations and HOAs can set shorter hours, and the stricter rule applies. The Town of Palm Beach also bans demolition entirely from November 1 through April 30 under Ordinance 15-2026, and has separate summer hours.
This time of year
Holiday and season rules that catch crews off guard
Thanksgiving is more than one day in some towns
The Town of Palm Beach's 2026 calendar bars construction on the Wednesday before Thanksgiving, Thanksgiving Day and the Friday after. Bay Harbor Islands also takes Thanksgiving and the day after off, and Golden Beach bans demolition on Thanksgiving.
The last week of December in Palm Beach
The Town of Palm Beach blocks construction on December 24 and 25, on December 28 through 30 under Ordinance 7-2025, and on December 31. Coral Gables and Bay Harbor Islands also treat December 24 as a holiday.
Miami Beach's right-of-way moratorium
Miami Beach suspends all construction in the public right-of-way during set periods: Thanksgiving week (November 23 to 29, 2026), Art Week (November 30 to December 6), the G20 Summit week (December 14 to 20) and the holiday break (December 21, 2026 to January 3, 2027). No lane, sidewalk or road closures, and barricades and equipment have to come out of the right-of-way.
Season in Palm Beach changes everything
From November 1 to April 30, the Town of Palm Beach allows construction only on weekdays from 9 a.m. to 5 p.m. and bans demolition entirely under Ordinance 15-2026. Plan a teardown on the island for the summer months.
Working outside the hours
Noise waivers, fines and who gets cited
City of Miami waivers take 15 business days
Work outside 8 a.m. to 6 p.m., or on a Sunday or federal holiday, needs a construction noise waiver under Sec. 36-6(c) of the city code. Apply at least 15 business days ahead. On private property, the city considers early starts from 6 a.m. to 8 a.m.; overnight work is limited to right-of-way work and emergencies.
In practice, Miami approves almost all of them
WLRN reported in June 2025 that of 1,135 waiver requests filed in the City of Miami since October 2023, none were denied and two were later revoked, even though the code ties waivers to conditions that endanger life or property.
Miami Beach fines climb fast
Miami Beach fines construction noise violations $250 for a first offense, $1,500 for a second, $3,000 for a third, $4,000 for a fourth and $5,000 for a fifth, after which the violator is treated as a habitual offender.
Other cities have their own paths
Coral Gables takes online requests for special or emergency hours. In West Palm Beach a building official can approve work outside the normal hours at a specific site, sometimes with notice to neighbors. Bay Harbor Islands fines start at $1,000, with stop-work orders for repeat violations.
Planning a demolition
How to keep a demolition on schedule and the neighbors calm
Check three sets of rules
The city's hours, any building or HOA rules, and any seasonal or right-of-way restrictions. The strictest one wins.
Count the real working days
In Bay Harbor Islands, a Saturday-free week has five working days. In the Town of Palm Beach in winter, it has five shorter ones. Build that into the timeline before you promise a builder a start date.
Time the loud work and the trucks
Machine work, hammering concrete and loading containers make the most noise. Schedule them inside the allowed hours, and remember that truck arrivals count too.
Tell the neighbors before you start
A short note with the dates, the hours and a phone number heads off most complaints.
Sources
The official pages we used
Official sources
Each city's own page or code section, checked in November 2026. Hollywood, Aventura and Golden Beach come from our city pages.
Related
Keep reading
Demolition next door
What neighbors can expect and what they can ask for.
Best time to demolish in Florida
Seasons, weather and permit timing.
Demolition timeline in South Florida
How long each stage really takes.
Surprising demolition rules in South Florida cities
The local rules that catch contractors off guard.
Common questions
Frequently asked questions
What time can construction start in Miami?
In the City of Miami, construction is allowed Monday through Saturday from 8 a.m. to 6 p.m. Earlier starts, from 6 a.m., and work on Sundays or federal holidays need a construction noise waiver, which should be requested at least 15 business days ahead.
Can construction happen on Sunday in Fort Lauderdale?
Yes. Fort Lauderdale allows construction from 8 a.m. to 7 p.m. Monday through Saturday and from 10 a.m. to 7 p.m. on Sundays.
What are the construction hours in Miami Beach?
In residential zones, 8 a.m. to 6 p.m. on weekdays and 10 a.m. to 4 p.m. on Saturdays. In commercial and mixed-use zones, 7:30 a.m. to 6:30 p.m., or 7:30 p.m. during daylight saving time. No construction noise is allowed on Sundays or national holidays.
Can you do construction on Thanksgiving in South Florida?
In many places, no. Miami Beach, Coral Gables and Bay Harbor Islands ban construction on federal or town holidays, the City of Miami requires a noise waiver, and the Town of Palm Beach blocks the Wednesday before Thanksgiving through the Friday after. Check your city's rules before scheduling work that week.
What are the construction hours in Hollywood, Florida?
Under Hollywood's noise ordinance, demolition is allowed from 7 a.m. to 6 p.m. Monday through Friday and 8 a.m. to 6 p.m. on Saturday. Sunday work needs written approval from the city's Chief Building Official.
What are the construction hours in the Town of Palm Beach?
From November 1 to April 30, construction is allowed only Monday through Friday from 9 a.m. to 5 p.m., with none on weekends or town holidays, and demolition is banned entirely during that season. Summer hours are different.
This article is general information, not legal advice. It reflects the City of Miami's construction noise waiver page (Sec. 36-6(c)), Miami Beach's noise control rules (Secs. 46-156 and 46-159), Coral Gables' construction work hours page, Bay Harbor Islands Code Sec. 12-26, Golden Beach Code Sec. 14-84, Hollywood's noise ordinance, Aventura's construction hours, Fort Lauderdale's noise ordinance page, West Palm Beach's code enforcement FAQ, the Town of Palm Beach's construction working hours (Rev. July 16, 2026) and WLRN's June 2025 reporting, as checked in November 2026. Hours change, and holidays move from year to year, so confirm with the city before you schedule work.